Question 142

The project manager asks the risk manager to determine the initial risk assessment for a six month conduct the related analysis? (Choose two.)

    Correct Answer: B, E

    To determine the initial risk assessment for a project, it is essential to use brainstorming as it is a common technique to identify potential risks through collaborative discussions. Additionally, the Work Breakdown Structure (WBS) provides a detailed breakdown of the project's scope into smaller, more manageable components, which helps in identifying specific risks associated with different parts of the project.

Discussion
MikeMarloOptions: BE

For an initial Risk Assessment, the two needed things here are: Brainstorming and WBS in order to start with something.

Azharmak

Question not understood!

Lunk

This is a poorly phrased question.