Exam PMI-SP All QuestionsBrowse all questions from this exam
Question 8

You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a standard for all future organizational projects based on your project's performance, approach, and implementation of project processes. All of the following should be included in your project's process improvement plan except for which one?

    Correct Answer: D

    Identification of project risks is not part of the process improvement plan. Identifying risks falls under risk management and is documented in the risk register. The process improvement plan focuses on refining existing processes, which includes defining process boundaries, configuring processes, and setting targets for improved performance.

Discussion
omankomanOption: D

D is right answer.