Question 144

During a project review meeting, stakeholders are making decisions on how to respond to known and new risks encountered during project execution. Which three artifacts should the stakeholders review? (Choose three.)

    Correct Answer: A, C, D

    The Risk Register is essential as it contains details about all identified risks, including their status and responses. The Risk-adjusted backlog is crucial in Agile projects to ensure risks are included in planning and prioritization. The Assumption log helps validate initial assumptions and identify new risks, making it vital for risk response decisions.

Discussion
MikeMarloOptions: ACD

Sorry! Risk Register Risk Adjusted Log >> Agile Backlog with included risks >> another way to have risks in the planning. Ensuring risks are considered, we can make decisions on how to respond to risks. Assumptions log Question 284 >> Risk Adjusted Backlog. I got confused because answer is/was Change Log and although Change Log is important to track changes, it is not so important to make decisions about Planning Risk Responses

MikeMarloOptions: ABD

Risk Register >> Where all the risks are Change Log >> Tracking Changes Assumption Log >> Validating assumption and identifying new risks