You must propose an Oracle Data Guard configuration for a database supporting an OLTP workload that meets these permanent requirements:
1. Data loss is not permitted.
2. Read-only applications should not connect to the primary database instance.
Additionally, there are these requirements, only one of which is ever done at any one time:
3. It should be possible to apply and test designated patches with a minimum amount of downtime.
4. Upgrading to a new database release should be performed with the least possible amount of downtime.
5. New application software releases should be tested against an exact up-to-date replica of the production database.
You propose a primary database with one physical standby database configured in Maximum Protection mode.
Which requirements do you meet?