Question 268

A company uses planning optimization in Dynamics 365 Supply Chain Management.

A new item is set up for production with a bill of materials (BOM) and is included in planning optimization.

You need to identify the planning output for the item.

What are two parts of the output? Each answer represents a partial solution.

NOTE: Each correct selection is worth one point.

    Correct Answer: B, D

    When planning optimization is used in Dynamics 365 Supply Chain Management for a new item with a bill of materials (BOM) included in planning, two key parts of the output are production orders and action messages. Production orders are generated to schedule and manage the manufacturing of the item, aligning with its BOM requirements. Action messages are recommendations or instructions that assist in optimizing and adjusting the production plan to ensure efficient workflows and inventory management. These components are crucial for maintaining smooth production operations and timely fulfillment of manufacturing requirements.

Discussion
KandakkapillilOptions: BD

As it is a BOM item the output will be a Production Order and not a Purchase Order

bromark10Options: BD

It should be production orders and action messages..

usmanshafiq00Options: BD

it should be production order and action message. purchase order is not part of production

BlesafOptions: BD

Production orders are created to manufacture the item, and action messages provide recommendations or instructions related to the item's planning and replenishment. This combination helps manage production and inventory effectively.