Exam C1000-140 All QuestionsBrowse all questions from this exam
Question 44

A QRadar deployment professional needs to transfer the configuration of a distributed environment (one Console and one EP, not using HA) onto an All-in-One (AIO) system to run some forensics against data that will be added later.

What approach should the deployment professional suggest for building the new AIO?

    Correct Answer: B

    The configuration of the source environment should be backed up and then restored on the new AIO. After the system is up, the eProcessor (EP) can be removed by using the GUI. This method is straightforward and commonly recommended as it allows full transfer of configuration settings and can be managed within the user interface without requiring backend commands, which minimizes the risk of errors.

Discussion
ChandanaaOption: B

Answer should be "B"

ChandanaaOption: C

I guess the answer is "C"

Chandanaa

sorry, answer should be "B"